MISSION WWTP PLANT LIFT SELF PRIMING PUMP

Location: Mission,TX,UNITED STATES
Zip: 78572
Project Type: New Construction
ProjectUse: Water & Sewage Treatment
Project Budget: 1,000,000 to 10,000,000 USD
Contact Method : With Contact Details
Name : Eduardo Belmarez , 1201 E 8TH ST , MISSION , TX , 78572-4130 , Ph: 956 580-8667

Posted on :May 12, 2012
Last Updated :May 12, 2012
Bid Date: 23/05/2012

Description:

Water Treatment,Sewage Treatment

WWTP PLANT LIFT SELF-PRIMING PUMP INSTALLATION
The project involves the installation of two 10” self-priming centrifugal
pumps at the plant lift station that have been pre-purchased and are onsite. Two existing
pumps will need to be moved and the pump base will need to be modified to accommodate
the self-priming pumps. Pumps motors pre-purchased and onsite will need to be lifted and
anchored into place. There is a small amount of mechanical work involving piping and valves
necessary to connect the pumps to the existing suction and discharge piping. Conductors will
need to be extended a short distance to the pumps to power the motors. In short, the project
requires the completion of all work necessary to install the two self-priming pumps and make
them fully operational.