Framing

Floor System:

Termite shield: P / roll Lf = # of rolls
Sill sealer: same as above
Sill plates: P = Lf, send appropriate lengths (2 x 6, normally treated)
Girders: house length x 3 = Lf, send appropriate lengths
Floor joists: house length x .75 + 1 = # for 1 set, 16� o.c.
Bridging: # of joists x 2 = pcs. / 50 = bundles (spans over 12� may require more, check plans)
Box sill: house length x 2 = Lf (same dimensions as floor joists)
Joist hangers: 2 per joist
Nails: joists: 20 lbs. per MBF (16d)
bridging: 2 lbs. per 50 pcs. (6d)
Sub Floor:

Plywood underlayment: sq. ft. x 1.05 / 32 = pcs.
Nails: 20 lbs. per M Sq. ft.
Adhesive: # sheets plywood / 5 = tubes
WALL SYSTEM :

Plates: P + IP x 3 = Lf (send 3 lengths)
Studs: 16� o.c.: P + IP x 1.10 pcs.
24� o.c.; P + IP x 0.80 pcs.
Nails: Wall assembly: 10 lbs. per 100 studs (16d)
Attach walls to subfloor: 2 lbs. per 100 studs (16d)
Headers: R.O. + 3� x 2 = Lf